L&T CTS Sholinganallur

Supaflo PC711 cut cement and shortened the prestressing cycle for M50 slab concrete

Project type
Commercial & Retail
Location
Chennai, India
Year
2014
Products
Supaflo PC711, Flo-Add 1, Cempatch HM and others
Cognizant office building at Sholinganallur, Chennai (open the photo larger)
Cognizant office building at Sholinganallur, Chennai

The challenge

The main design focus was the prestressed slabs, chosen for strength, durability, stiffness and serviceability. The specified concrete was M50, with at least 30 MPa after 48 hours. The original mix used 490 kg/m³ of cementitious material, a water cement ratio of 0.36 and an SNF admixture, and took three to four days to reach 30 MPa. The challenge was to reach strength sooner without raising concrete cost per m³ through more cement.

The DCP solution

The DCP technical team proposed Supaflo PC711, a high range polycarboxylate (PC) admixture, for evaluation by Larsen & Toubro. Trials at a water cement ratio of 0.35 with Supaflo PC711 reached the required compressive strength in a shorter time with less cementitious material.

DCP products used

Admixtures Supaflo PC711 High performance concrete admixture based on polycarboxylic polymers for concrete with low water cement ratio Product page: Supaflo PC711
Grouts and anchors Flo-Add 1 Expansive and plasticising grout admixture Product page: Flo-Add 1
Concrete repair Cempatch HM Non-shrink general purpose high strength repair mortar (Micro Concrete) Product page: Cempatch HM
Named in the project Supaflo SPL Not in the SpecHub product library. Ask DCP for the current product.

How it was applied

  1. Original mix: cement and fly ash 490 kg/m³ (415 + 75), free water 175 litres, SNF at 1.2% by weight of cement, CA:FA 60:40, slump 120 mm at 90 minutes.
  2. Final mix: cement and fly ash 470 kg/m³ (380 + 90), free water 165 litres, Supaflo PC711 at 0.55% by weight of cement, CA:FA 62:38, slump 150 mm at 90 minutes.
  3. Both mixes: 20 mm and 10 mm aggregate at 60:40, 100% crushed sand.

The result

The required strength was reached after 2 days instead of 3 to 4, the contractor achieved its prestressing cycle and the cost of the concrete fell noticeably.